After a Florida Condo Milestone Report: SIRS, Repairs and Permits

Structural and MEP engineering services in Florida for residential and commercial projects

After a Florida condominium milestone inspection, the association has 45 days to send every unit owner the inspector’s summary. If the report finds substantial structural deterioration, a Phase 2 inspection follows, and the repairs it calls for must be started within 365 days. A structural integrity reserve study (SIRS) then sets how much the association must save to keep the building’s main systems in repair.

This article covers what happens after the report: the deadlines in Florida law, how recommendations become a repair scope and permit drawings, and what the board should ask its engineer. It summarizes Section 553.899 and Section 718.112(2)(g) of the Florida Statutes as published for 2025. It is general information, not legal advice. Your association’s attorney and your local building department have the final word.

Which Buildings Fall Under the Milestone Rules

Section 553.899 applies to buildings three habitable stories or more in height, as the Florida Building Code measures them, that are under condominium or cooperative ownership. The first inspection is due by December 31 of the year the building reaches 30 years of age, counted from the date the building was first approved for occupancy. After that, an inspection is due every 10 years. A local enforcement agency may move the first inspection to 25 years where local conditions, such as closeness to salt water, justify it. The local agency may also extend a deadline for good cause.

The inspection must be performed by an architect or engineer. A team may do the work, as long as one architect or engineer is in responsible charge. Smaller residential buildings of one to four units, with three or fewer habitable stories, are exempt.

Phase 1 and Phase 2

Phase 1 is a visual examination of the building’s habitable and nonhabitable areas. It is meant to find “substantial structural deterioration”, which the statute defines as substantial structural distress or substantial structural weakness. Surface cracks and other cosmetic defects do not count, unless the inspector decides they point to deterioration.

Phase 2 is required only if Phase 1 finds substantial structural deterioration. It is a closer look at the affected areas and can include destructive or nondestructive testing at the inspector’s direction, such as concrete cores, chipping to expose reinforcing steel, or other tests. Within 180 days after the Phase 1 report, the Phase 2 inspector must give the local enforcement agency a progress report with a timeline for completing Phase 2.

Under the statute, each report must:

  • Be prepared by an engineer or architect.
  • Describe the type of inspection.
  • Identify any substantial structural deterioration, its extent and the recommended repairs.
  • State whether unsafe or dangerous conditions were observed.
  • Recommend repairs for damage that is not substantial deterioration.
  • List items that need further inspection.

What a Milestone Report Must Contain

Florida law sets a minimum content for every phase one and phase two milestone report. The report must:

  • State the manner and type of inspection the report is based on.
  • Identify any substantial structural deterioration, describe how far it extends, and recommend repairs for it.
  • State whether unsafe or dangerous conditions, as the Florida Building Code defines them, were observed.
  • Recommend remedial or preventive repairs for items that are damaged but are not substantial structural deterioration.
  • Identify and describe any items that need further inspection.

The engineer or architect who performed the inspection also prepares a separate summary of the material findings and recommendations. These recommendations are the starting point for the repair scope and the repair drawings.

Who Receives the Report

The inspector submits the report and its summary to the association, to any other owner of part of the building that is not under the association, and to the building official of the local government. The association then shares the summary with unit owners as the statute requires. Local departments set up their own way to receive reports. The City of Tampa, for example, has milestone reports filed under a record in its Accela online permitting system and posts contacts for associations with questions. When repairs follow, the repair drawings go to the same department for a building permit, and we prepare those drawings from the report’s findings.

Deadlines After the Report

StepDeadline in Section 553.899
Association notifies unit owners that an inspection is requiredWithin 14 days of the local agency’s notice
Phase 1 inspection completedWithin 180 days of the owners receiving that notice
Phase 2 progress report to the local agency (if Phase 2 is needed)Within 180 days of the Phase 1 report
Inspector’s summary distributed to every unit owner and posted at the propertyWithin 45 days of receiving the report, whatever its findings
Repairs for substantial structural deterioration commencedWithin 365 days of receiving the report

If the association has a website, it must post the full report and the summary there. If proof that repairs were scheduled or started is not submitted, the local enforcement agency must review the building and decide whether it is unsafe for human occupancy. Local governments set their own procedures, penalties and timelines within the statute, so the building department’s milestone page is the next place to look.

Miami-Dade and Broward counties also run their own long-standing building safety inspection programs. Associations there should confirm how the county program and the state milestone requirement line up for their building.

How the SIRS Fits In

Section 718.112(2)(g) requires a structural integrity reserve study at least every 10 years for each condominium building of three habitable stories or more. The study is based on a visual inspection. It covers these items:

  • Roof.
  • Structure, including load-bearing walls and other primary structural members.
  • Fireproofing and fire protection systems.
  • Plumbing.
  • Electrical systems.
  • Waterproofing and exterior painting.
  • Windows and exterior doors.
  • Any other item with a replacement cost over $25,000 whose failure would affect those items.

A SIRS must be performed or verified by an engineer or architect, or by a credentialed reserve specialist or reserve analyst.

For associations that existed on or before July 1, 2022, the statute set December 31, 2025 for the first SIRS. An association that also has a milestone inspection due by December 31, 2026 may do both at the same time, but no SIRS may be completed later than December 31, 2026. A milestone inspection from the past five years may replace the visual inspection part of the SIRS. Within 45 days of receiving the study, the association must give each owner a copy, or notice that it is available, and file a statement with the Division of Florida Condominiums.

For a budget adopted on or before December 31, 2028, the statute lets owners vote to let the board temporarily pause reserve contributions for no more than two consecutive annual budgets. This is allowed only if a milestone inspection was completed within the previous two calendar years, and a majority of the total voting interests must approve it. Read the exact conditions in the statute with your attorney. The Division of Florida Condominiums, Timeshares, and Mobile Homes (part of DBPR) publishes plain-language guidance on these rules.

Who oversees condominiums in Florida? Condominium associations are regulated by the state’s Department of Business and Professional Regulation, through its condominium division, which also posts information on milestone inspections and structural integrity reserve studies. Building safety itself, including the milestone program, is handled by the local building official under the Florida Building Code and the statute.

From Recommendations to a Repair Scope

A milestone report says what is wrong and what kind of repair is needed. It is not a set of construction documents. Between the report and the 365-day deadline, the association usually needs:

  1. A defined repair scope. The engineer maps each deficiency to a location and quantity: for example, balcony slabs with spalled concrete, columns with exposed reinforcing, or walkway edges with cracking. Where the extent is unknown, the drawings set unit-price items for the contractor to measure during demolition.
  2. Repair drawings and specifications. These show the repair methods, such as concrete removal and patching, reinforcing replacement or supplemental bars, corrosion protection, membrane and sealant work, and railing anchorage. They also cover shoring needs and the order of work.
  3. A building permit. Most structural repairs need a permit under the Florida Building Code. The drawings go to the building department that has jurisdiction, and plan review comments are answered before work starts.
  4. Bidding. The same drawings let several contractors price the same scope. The statute has disclosure rules for design professionals and contractors who bid on work recommended in a milestone report, so the board should ask its attorney how those apply.
  5. Construction-phase observation. Hidden conditions are common in concrete repair. The engineer reviews what demolition exposes and adjusts details as needed.

DBPR’s guidance also notes that, after the repairs, a professional reinspects the building and provides an amended report. Planning for that closing step from the start avoids a second round of surprises.

Questions a Board Should Ask Its Engineer

  • Which findings are substantial structural deterioration, and which are maintenance items?
  • Does any area need shoring or restricted use now, before repairs?
  • Which repairs can be grouped into one permit, and which need separate permits?
  • How will quantities be measured and paid, so hidden damage does not become a dispute?
  • How do the repairs line up with the SIRS items and the reserve schedule?

How Chrome Stone Helps

Chrome Stone Structural does not perform milestone or county building safety inspections. Our work begins once you have the report. From Miami we prepare the structural repair drawings, calculations and permit documents that put its recommendations into practice, and we answer plan review comments for condominium and multifamily buildings across Florida. We work in Miami-Dade, Broward and Palm Beach counties, and in Tampa, St. Petersburg, Southwest Florida, Orlando and Jacksonville. See our Florida structural engineering overview, or send us the report summary to start.

Frequently Asked Questions

How long does a condo association have to start repairs after receiving the milestone report?

Section 553.899 requires repairs for substantial structural deterioration to be commenced within 365 days of receiving the report. Local governments adopt the ordinance that enforces it and may set their own procedures.

When is Phase 2 required?

Only when the Phase 1 visual inspection finds substantial structural deterioration. Phase 2 can include destructive or nondestructive testing, and a progress report is due to the local agency within 180 days of the Phase 1 report.

Do unit owners get a copy of the milestone report?

Every owner must receive the inspector’s summary within 45 days, whatever the findings. If the association has a website, the full report and the summary must be posted there.

What is the deadline for a structural integrity reserve study?

The statute set December 31, 2025 for associations that existed on or before July 1, 2022. An association with a milestone inspection due by December 31, 2026 may complete both together, but no later than December 31, 2026.

Can the engineer who wrote the milestone report also design the repairs?

Section 553.899 has disclosure rules for design professionals and contractors who bid on work the report recommends. Ask your association attorney how they apply before you hire the same firm for both.

Do milestone repairs need a building permit?

Most structural repairs need a permit under the Florida Building Code, with engineered drawings. Confirm the scope with your local building department before work starts.

What is a milestone report in Florida?

The written report from a phase one or phase two milestone inspection. It describes the inspection, identifies substantial structural deterioration and unsafe conditions, recommends repairs, and lists items that need further inspection.

Sources

We post one project and one code or engineering note every week on LinkedIn. Follow Chrome Stone on LinkedIn

Request a Quote

Discuss your engineering project

Tell us where your project is located in California or Florida and which engineering services you need.

  • Project city and state
  • Building type and proposed work
  • Required engineering disciplines
  • Architectural or existing-condition drawings available

Prefer to call? +1-279-221-5279


    We will use this address to respond to your inquiry.


    Add it if you prefer a call back.


    City only. A full property address is not needed for this first inquiry.

    Engineering support needed

    California Title 24 applies to California projects only.


    Briefly describe the building, proposed work, and any questions. Do not include passwords, payment details, or confidential documents.

    Add project stage or other details (optional)


    Leave blank if unknown.


    Tell us what the date relates to. The team will confirm feasibility after reviewing the scope.

    We use these details to review and respond to your inquiry. Read our Privacy Policy.

    While we review your project, follow Chrome Stone Structural on LinkedIn for new projects and code updates. Follow us on LinkedIn